The choice of work technology is determined by the permanent way parts which are replaced:

Track renewal

The entire track panel is replaced. As a rule, this also entails ballast cleaning of the track section.

Track laying

A new track panel is laid on a prepared formation with the first layer of ballast.

Track removal

An existing track panel including the ballast bed is completely removed.

Sleeper exchange

Old sleepers are replaced with new ones, without replacing the rails.

Rail exchange

Old rails are replaced with new ones, without replacing the sleepers.

Track renewal with ballast bed cleaning

Both measures can be performed at the same time.

Track renewal with ballastcleaning and an integrated first tamping cycle

Bundling work sequences simplifies worksite logistics and leaves you with a track open for traffic.

All of these material-intensive and difficult activities – previously hard manual labour – are now carried out by powerful machine systems.

“Travelling and building” is by no means just a conflict of objectives between operations and maintenance. “Travelling and building” is also a key skill in the construction sector. Everyone involved can profit from that, including customers and stakeholders, even society and the environment.

from Kapazitätsschonender Gleisumbau
(Hüper, Tesch, Uhlenhut; GRT Global Rail Academy and Media GmbH, 2022)